  • From Qualification to PPQ: The Bigger Picture of Paperless Validation

    From Qualification to PPQ: The Bigger Picture of Paperless Validation

    When organisations discuss paperless validation, Computer System Validation (CSV) is almost always the first topic on the table. This comes as no surprise — electronic hardware and software have become deeply embedded in every facet of modern manufacturing. Yet, while digital systems serve an important supporting function, they are not what ultimately produces a product. The most critical component in any manufacturing operation is the equipment itself. Without equipment, nothing gets made. That is why paperless validation should focus strongly on the equipment level.

    Whether introducing new equipment or modifying an existing asset, the end goal seems to be always the same: to qualify the equipment or update its qualification records. In the case of an existing piece of equipment, this might involve changes to the PLC logic or the replacement and upgrade of key components.  But is that enough?

    What matters most when teams make these changes is not simply whether they have updated the qualification records correctly. Far more important is the effect these changes have had on process parameters. Regulators and auditors are primarily concerned with whether manufacturing and cleaning processes continue to perform consistently — whether there is variation within a batch and from one batch to the next.  That is the question of interest.

    This article addresses an often-missed link in this chain: the data that the process validation team needs after the equipment qualification team completes its work. This handover of critical information is, in reality, the most important activity in the entire process.  Because it determines whether the process remains compliant. One cannot operate equipment in a range that was not qualified. 

    Process Paramters

    Process parameters are not merely operational settings — they are the critical link between equipment performance and product quality. They have a direct and measurable effect on the Critical Quality Attributes (CQAs) that define whether a drug product meets its specification. A shift in even 1 process parameter, however small, can alter the quality profile of the final product. This is precisely why teams must carefully assess every equipment modification and consider its downstream impact on process parameters and, ultimately, patient safety.

    The same principle applies when purchasing new equipment. Does the new equipment truly match the existing one? Teams must analyse and document this comparison before moving forward with procurement.

    Consider a real example. A site plans to replace an old granulation mixer with a new model featuring an updated, more efficient bowl design and a PLC-controlled mixing cycle.

    The new mixer requires equipment qualification before the site can put it into production. But qualification should not be the starting point. Before defining the additional equipment and software qualification steps, the team should ask at least two questions to determine what it needs to demonstrate through PPQ and CV runs to ensure the product meets its specifications, both in-process and in the finished product.

    1. Is the new equipment identical to the equipment it will replace? If differences exist, what are they? How could those differences affect product quality? For example, has the bowl geometry changed in a way that alters the product-contact surface area or mixing dynamics?
    2. Will the site purchase the equipment “off the shelf,” or will the supplier customise it?

    The new bowl design may alter the fundamental fluid dynamics and mass movement within the mixer. As a result, the existing ranges for critical process parameters such as mixing speed, shear profile, mixing time to endpoint, and torque curves may no longer remain valid. The team would therefore need to repeat PPQ runs on the new equipment to demonstrate that the process still meets the required product specifications.

    A change in PLC logic could also fundamentally alter how the equipment controls and sequences the process. The original PPQ runs used a specific set of automated controls, including defined ramp rates, hold times, interlocks, alarm thresholds, and parameter sequencing. These controls consistently delivered product that met its CQAs.

    If the new PLC logic manages these same parameters differently — perhaps through different control algorithms, tighter or wider deadbands, altered timing sequences, or different response characteristics to process deviations — the previously validated process no longer represents the new operating conditions. The team must therefore conduct new PPQ runs to demonstrate that the new control logic, while governing the same critical process parameters, still produces a product that consistently meets its drug product specifications, batch after batch. Parameters, still produces a product that consistently meets its drug product specifications, batch after batch.

    3 Runs Completed Successfully – Tell us more about the process

    Three successful PPQ runs may satisfy the immediate qualification requirement, but they do not provide the full picture. They represent a limited snapshot — a demonstration that the process can produce compliant product under controlled conditions on three occasions. What they cannot tell us is how tightly the product specification remains within tolerance over time. This is precisely why Continued Process Verification (CPV) exists — to confirm that the results demonstrated during the three PPQ runs remain consistent at batch fifty, batch one hundred, and beyond. Without sustained monitoring during the CPV stage, those three successful runs can create false assurance while leaving the risk of slow, undetected drift from the drug product specification unaddressed.

    The team must not only monitor the process after PPQ runs; it must also monitor the equipment and the PLC logic that controls it. PLC logic does not remain static. Software updates, firmware patches, sensor recalibration, and even subtle electrical degradation can change how the control system behaves over time. A timing sequence can drift by milliseconds, maintenance can inadvertently overwrite an alarm threshold, or a control loop can respond differently to input signals — and any of these changes can shift process parameters without triggering a single deviation.

    Equally, the physical equipment is subject to wear and tear that no PLC can detect — bowl surfaces that degrade over time, impeller blades that erode and alter shear profiles, seals that harden and introduce dead spots, or contact surfaces that pit and roughen, changing both product interaction and cleanability. If the organisation monitors only the product and the process but neglects the equipment’s control logic and its physical condition, it creates a blind spot where the root cause of a future quality failure — whether digital or mechanical — will remain invisible until it manifests as out-of-specification product in the hands of the patient.

    Paperless Validation Must Evolve Too

    If validation is a lifecycle, then paperless validation must evolve with it. The objective is not simply to replace paper with electronic records. It is to make validation easier to manage throughout its entire lifecycle — from initial qualification through process validation, change control, monitoring and ongoing verification.

    This means paperless validation must look beyond electronic components, software, and PLC logic alone. The equipment in its entirety must be qualified — its mechanical systems, its control logic, its physical condition and its interaction with other equipment. This is not a novel concept. ISPE Baseline Guide Volume 5 on Commissioning and Qualification makes this point clearly: qualification should encompass the complete equipment system, not just its individual automated elements. A paperless approach that captures only the digital layer while ignoring the physical asset beneath it is not simplifying the lifecycle — it is leaving critical gaps in it.

    Positioning PQMS Suite

    This is where an integrated platform such as Quascenta’s PQMS Suite can support the broader validation lifecycle.

    ValDoc Pro supports all qualification & computer system validation activities; eProcess Pro manages PPQ runs and CPV runs; eResidue Pro supports cleaning process management; eLog Pro enables electronic logging and recording of routine operational activities to support ongoing monitoring and control; and QMS Pro manages the change control, CAPAs, and non-conformances that changes like this can trigger.

    Together, these capabilities allow organisations to move beyond simply converting paper-based validation tasks into electronic format. Instead, they create a connected digital environment that brings qualification, process validation, cleaning validation, change control, and ongoing monitoring together within one coherent, living system.

    ravi

    September 1, 2026
    Uncategorized
    csv, digital transformation, digitilization, Equipment Qualification, paperless validation, Pharmaceutical Validation, Quality Assurance
  • Equipment Classification: The Decision That Drives Qualification

    Equipment Classification: The Decision That Drives Qualification

    Before an equipment qualification protocol is drafted, here’s a question worth asking: Does every piece of equipment have to go through a qualification lifecycle requiring the same resources, time, and effort, or would commissioning suffice for some?

    Some never pause to question whether full commissioning and qualification are truly necessary. Instead, the default option of qualifying every asset is exercised because it appears comprehensive on paper. But is this approach the most efficient use of time and resources, or could a more targeted strategy deliver faster, equally reliable outcomes?

    Equipment classification provides a structured way to answer that question. As outlined in the ISPE Baseline Guide Volume 5, the System Classification framework classifies equipment as Direct Impact or Not Direct Impact, providing the basis for determining the qualification strategy.

    System Classification According to ISPE

    Classification comes down to answering eight questions — a YES to any one of them makes the equipment Direct Impact. All eight have to come back NO before it can be Not Direct Impact. (ISPE Baseline® Guide Volume 5, Section 3.3)

    1. Does it control a CPP, or otherwise serve a defined CQA?
    2. Does it have direct contact with the product or process stream?
    3. Does it produce an excipient, ingredient, or solvent—Water for Injection being the obvious one?
    4. Is it used for cleaning, sanitising, or sterilising?
    5. Does it maintain an environment—temperature, humidity, an aseptic zone — that’s a CPP for the process?
    6. Does it generate or hold data used to accept or reject the batch, or fall under 21 CFR Part 11 or EU GMP Annex 11?
    7. Does it provide the container closure or product protection?
    8. Does it apply or check product identification with no independent verification elsewhere?

    Classification Outcomes

    Every piece of equipment gets sorted into one of two categories based on how it answers those eight questions — Direct Impact or Not Direct Impact.

    Direct Impact (DI)Not Direct Impact (NDI)
    Qualified and commissioned Commissioned only
    Scope set by CQA/CPP risk to the productScope set by SME judgment and HSE criticality
    System Risk Assessment identifies the CDEsSME review sets the commissioning scope
    Full C&Q documentation packageCommissioning documentation only

    Consider the following examples:

    • A vial filling machine answers YES at Q2 alone—it’s in direct contact with the product during filling, and a failure there is a direct line to product quality. One YES is enough. It’s Direct Impact and goes through the commissioning and qualification workflow.
    • A shrink-wrapping machine sits downstream; it bundles product that’s already capped, stoppered, or sealed. It doesn’t touch product, so Q2 is a clean NO. The question worth pausing on is Q7—product protection. Shrink film does protect the product in transit, so a quick read might call this a YES. But Q7 asks whether this equipment provides the seal on which product quality depends, and the upstream capping or stoppering step already provides that seal. The shrink wrap is a secondary bundle, not the barrier the product relies on. Q7 comes back NO, and so does the rest. The shrink-wrapper is Not Direct Impact. It still goes through commissioning—it just doesn’t go through qualification.

    Where classification gets genuinely tricky

    Most equipment can be classified with relative ease. Utilities, however, often require a closer evaluation because their classification depends on how they support the process.

    1. Utilities controlling critical process parameters: Product contact alone does not determine classification. Utilities that control Critical Process Parameters (CPPs) may still be classified as Direct Impact.

    Example: A chilled water system cooling a jacketed reactor may never contact the product, but if it controls the reaction temperature (a CPP), it is classified as Direct Impact.

    • Utilities with multiple points of use: The same utility can serve both Direct Impact and Not Direct Impact applications. Classification should be based on the specific point of use rather than the utility itself.

    Example: Compressed air used to dry product-contact equipment after cleaning may be classified as Direct Impact. The same compressed air used only to operate non-product-contact equipment is Not Direct Impact.

    • Function over equipment type: Classify systems such as nitrogen, vacuum, or compressed air according to their function in the process, not their names.

    Example: Nitrogen used for product blanketing is Direct Impact, whereas nitrogen used only for line pressurisation may not be.

    The Bottom Line

    The most effective qualification programmes do not qualify every equipment. They are selective. Equipment classification provides the framework for making that decision consistently, ensuring that the qualification effort, project resources, and regulatory focus remain aligned with actual product and process risk.

    Reference

    1. ISPE Baseline® Guide: Commissioning and Qualification, Volume 5, Second Edition. International Society for Pharmaceutical Engineering (ISPE), 2019. ISBN 978-1-946964-23-6.

    ravi

    July 27, 2026
    Uncategorized
    digital transformation, direct impact, Equipment Qualification, GxP Compliance, ispe, not direct impact, pharmaceutical, Pharmaceutical Validation, Quality Assurance
  • Factory Acceptance and Site Acceptance Testing: Accelerating Equipment Qualification with ValDoc Pro

    Factory Acceptance and Site Acceptance Testing: Accelerating Equipment Qualification with ValDoc Pro

    https://www.pqms.com/wp-content/uploads/2025/12/FAT-SAT-Article-1.mp4

    Synopsis:

    “Suitable for the intended purpose/activities” is a core regulatory expectation for all pharmaceutical manufacturing equipment, and qualification is the documented proof that this is achieved. The qualification lifecycle starts with a User Requirement Specification (URS) document followed by a Functional Specification (FS).  Test Scripts are executed in IQ, OQ and PQ documents to demonstrate that the requirements noted in the URS are met. Because running IQ/OQ/PQ scripts at the manufacturing site is time-consuming and the responsibility falls only on the drug manufacturer, some of the effort can be shared with the vendor via Factory Acceptance Testing (FAT) and Site Acceptance Testing (SAT).  ValDoc Pro can streamline this process and build better compliance.  

    Regulatory Guidelines:

    121 CFR 211.63 states that “Equipment must be of appropriate design, adequate size, and suitably located to facilitate operations for its intended use”[2].  While the FDA recognises the advantages of FAT and SAT (mentioned in presentations by the FDA), there is no guideline that discusses this.   EU GMP Annex 15 & PIC/S explicitly state, in sections 3.4-3.7, that:

    • Equipment, especially if incorporating novel or complex technology, may be evaluated, if applicable, at the vendor prior to delivery.
    • Prior to installation, equipment should be confirmed to comply with the URS/ functional specification at the vendor site, if applicable.
    • Where appropriate and justified, documentation review and some tests could be performed at the FAT or other stages without the need to repeat on-site at IQ/OQ if it can be shown that the functionality is not affected by the transport and installation.
    • FAT may be supplemented by the execution of a SAT following the receipt of equipment at the manufacturing site.

    Leveraging Vendor Testing:

    The Factory Acceptance Test (FAT) is carried out at the vendor’s site and provides documented evidence that the equipment meets the user requirements and the vendor has fulfilled contractual responsibilities. A well‑planned FAT helps save time during qualification by identifying design issues, functional gaps, and integration problems before the equipment leaves the factory.   Sending the equipment back to the vendor to fix issues, especially when they are located across continents, is avoided through FAT.  Fat also provides the ability to check internal components of the equipment that one would not be able to reach at the site unless it is disassembled. 

    It is not necessary that a FAT test be performed for all equipment/systems.  That decision is left to the manufacturing site and its policy.  For a greenfield facility, a commissioning and qualification (C&Q) plan will direct this strategy.  A survey by ECA Academy in 2018 found that FAT is used by 37% of the companies surveyed, while 55% stated “it depends on the complexity of the project”. SAT was found to be used by 49% of those surveyed [5]. 

    Planning and preparation for the Factory Acceptance Test (FAT) are critical because the activity is conducted at the vendor’s site and involves budgeting for extra expenses on both sides. The decision to perform FAT is typically taken very early in the procurement lifecycle, during the development of the User Requirement Specification (URS) for the equipment.  The contract signed between the drug manufacturer and the vendor for an equipment includes scope of the FAT, responsibilities and the commercials.  The details of what is to be covered in FAT are put down in a protocol and frozen before approval of the design stage.  The site and the vendor have to agree on the features/functions to be demonstrated, parameter specification to be met, tests to be carried out, and identify the URS points covered by FAT.  The FAT protocol is sent to the drug manufacturer for review.  Once approved, then only the protocol can be executed.  During execution, the drug manufacturer representative(s) ideally should be present to at least to verify the minimum test requirements and resolve any deviations.  During and after the pandemic, many FATs have been conducted remotely, reducing travel and related expenses and making this an attractive option, particularly when organisations can leverage a wide range of digital tools and platforms to their advantage.

    The FAT protocol, once executed, is compiled along with attachments and sent to the site by the vendor for review.  In most cases, the equipment would have to be disassembled before shipping.  The documentation put together details equipment component labels and the process to follow to reassemble these components. 

    Similar to the FAT, the Site Acceptance Test (SAT) is not a mandatory test to perform.  The advantage of SAT is time savings.   A successful execution of the SAT protocol provides assurance that the equipment works as per specification post-transportation to the site.  While infrastructure, utilities, interfaces, etc, are defined in advance and agreed upon, surprises may crop up.  The SAT protocol also rechecks issues found during FAT.  These should be addressed before IQ begins.  In addition, the presence of the vendor’s team at the site speeds up testing, as that machine is very well known to them. 

    The SAT process follows the same overall approach as the FAT, but is performed at the manufacturing site rather than at the vendor’s facility. Whether a SAT will be performed should be defined in the C&Q plan and, preferably, specified in the URS and subsequently reflected in the contract.  SAT is led by the site, along with the vendor’s project/commissioning/service staff.  The SAT protocol is normally drafted by the vendor or the project engineering/validation team. 

    A decision that the site needs to take is whether they would like to leverage what was tested in FAT and SAT.  Most sites leverage the data from these tests.  The SAT protocol has many tests that overlap with what one would carry out under IQ and OQ protocols. 

    Accelerating FAT and SAT Efficiency with ValDoc Pro:

    ValDoc Pro is an easy to use Qualification management application that assists companies in digitizing their qualification workflow, from URS onwards through the entire lifecycle.  Its role-based access and real-time collaboration features enable vendors and manufacturers to coordinate FAT and SAT seamlessly.  Following are some of the advantages:

    • Vendor Access: Vendor can create, obtain site approval and execute FAT protocols within ValDoc Pro, with controlled access to designated folders/files. 
    • Site Review and Approval: The FAT protocol and FAT report can be submitted for review and approval online.
    • Seamless Flow: Generating the protocol by the vendor, review, execution and compilation all can be carried out seamlessly in ValDoc Pro. 
    • Sequential: ValDoc Pro ensures that the SAT protocol cannot be executed until the executed FAT report has been approved.  This ensures that the SAT protocol captures all relevant tests. 
    • Traceability Matrix: ValDoc Pro maintains a continuous link from URS through FAT/SAT to IQ/OQ/PQ, demonstrating to regulators that all user requirements were tested and all deviations addressed.

    Conclusion:

    Compared with relying solely on traditional IQ, OQ, and PQ, integrating FAT and SAT into the equipment qualification strategy allows issues to be identified earlier at the vendor and manufacturing site, limits risk, and reduces the amount of testing and troubleshooting that must be compressed into already busy commissioning windows. This upstream focus not only improves the quality of delivered assets but also frees site resources to concentrate on value-added verification and routine operation rather than firefighting late-stage gaps. ValDoc Pro-enabled FAT and SAT give pharmaceutical manufacturers a more efficient and compliant path to equipment qualification by moving protocols into a digitized, collaborative environment and enabling options such as Remote FAT, so teams can shorten timelines, reduce on-site disruption, and strengthen data integrity while maintaining full traceability from URS through lifecycle maintenance. In a landscape where each site-based role carries a greater workload, embedding FAT and SAT within a robust application like ValDoc Pro is not just an efficiency gain, but a strategic necessity for sustaining reliable, inspection-ready manufacturing.

    [1] FDA. Process Validation: General Principles and Practices. U.S. Food and Drug Administration.

    [2] “U.S. Food and Drug Administration. 21 CFR Part 211 – Current Good Manufacturing Practice for Finished Pharmaceuticals, §211.63 Equipment design, size, and location.”

    [3] European Commission. EU Guidelines for Good Manufacturing Practice for Medicinal Products for Human and Veterinary Use, EudraLex, Volume 4, Annex 15: Qualification and Validation. In operation since 1 October 2015

    [4] PIC/S. Guide to Good Manufacturing Practice for Medicinal Products, PE 009 (current version), Annex 15: Qualification and Validation

    [5] ECA Academy. FAT & SAT not frequently used as Part of Qualification – ECA Modern Qualification Survey Results. GMP News, gmp-compliance.org (2018)

    ravi

    December 12, 2025
    Uncategorized
    Equipment Qualification, Equipment Testing, GMP Compliance, Pharmaceutical Validation, Process Validation, Quality Assurance
  • Who is actually Responsible for the URS?

    Who is actually Responsible for the URS?

    Synopsis:

    Before purchasing an equipment, software or instrument, regulatory requirement mandates that one documents what is expected of the proposed acquisition. While it may be tempting to rely on vendors for this, as they understand their product, they do not understand the business requirements. That is why the User Requirement Specification (URS) must be authored by the team responsible for this new acquisition. This article explains why a user-driven URS ensures the acquired entity genuinely matches user needs, moving it from basic functionality to real-world fit

    It All Starts with a Need

    Picture this. You have been asked to put together a URS for a new equipment/software/instrument.  If this requirement was identical or similar to one that you have purchased in the past, that makes your task easier.  But what if this is a brand-new requirement.  Where do you start? 

    Appendix D5 from the ISPE GAMP 5 guidance document says it the best when it states that each user requirement should be specific, measurable, achievable, realistic, and testable.   It is also a good practice to prioritize the requirements, typically in two or three levels: (mandatory (high), beneficial (medium), and nice-to-have (low)) Or (mandatory (high) and nice-to-have (low)).

    The Easy Way

    As a vendor, we very often get asked to provide a draft URS that the regulated company then uses as a basis to draft the requirement.  Is this the right approach?  It sounds logical, right? After all, vendors are experts in the products they sell. But here’s the catch — they are experts in their product, not your business process.

    Sometimes we receive a URS that lists a specific brand or model, even including specifications unique to that brand. This is not the intended purpose of a user requirement, which should describe what is the needed functionally, not prescribe a particular vendor or solution.  When this happens, it limits the scope of solutions, undermines competitive assessment, and can introduce bias or compliance risks. Such requirements do not reflect true user needs but rather pre-select a solution, making it harder to compare alternatives and potentially exclude options that better meet functional requirements. GAMP 5 guidelines recommend describing functional needs in clear, objective terms, avoiding references to specific suppliers unless it is absolutely necessary to do so for business reasons

    Understanding the Roles the RACI way

    How do we decide the roles of various stakeholders.  A RACI Matrix, a simple chart that outlines who does what, breaks down the roles:

    Responsible:  Team/end users responsible for the business process.  The end users or process owners are usually responsible for drafting the URS since they know the operational needs best.

    Accountable: Manager(s) responsible for the business process.  Oversees URS creation and ensures it meets desired goals

    Consulted:

    • Other departments to provide their input/expertise as the acquired product may influence their workflows
    • IT team for software/IT hardware requirements to provide input on technical feasibility and rollout implications
    • CSV team for software to include regulatory requirements
    • Vendor – provide input and give technical advice. 
    • Informed-Vendors so as to put together a function requirement specification. 

    What do the Regulators Say?

    The FDA, the EMA and others, have made their stance clear: every system must be “fit for its intended use.”  That phrase — fit for intended use — is powerful. It means the system should perform exactly as needed for your specific products and processes.

    And who defines that intended use? Not the vendor — you do.

    According to the FDA’s General Principles of Software Validation and EMA’s Annex 11 on Computerised Systems, the responsibility for defining and confirming suitability lies with the regulated user organisation for computerised systems.  But that principle doesn’t stop there. Under broader GMP guidance, such as Annex 15 on Qualification and Validation, the manufacturers are responsible for ensuring equipment is suitable for its intended purpose and for defining its requirements in a User Requirements Specification (URS) or functional specification.

    In short, the user determines what’s needed; the vendor shows how their product meets those needs.

    Why Ownership Matters?

    When the customer owns the URS, everything aligns. The equipment fits its real operational needs, and the system passes regulatory scrutiny because it was built for its true purpose. And most importantly, it saves time, money, and frustration down the road.

    When vendors take over the URS, it might seem faster, but it’s like letting someone else write your recipe — you’ll never get the exact flavour you wanted.

    ravi

    November 9, 2025
    Uncategorized
    Equipment Qualification, GMP Compliance, Pharmaceutical Validation, Quality Assurance, URS, User Requirement Specification

Powering Quality from Lab to Label © 2025, Quascenta Pte. Ltd.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behavior or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}